Hey uo om just wondering how u guys go about pricing tonremove the old render first as u never know how hard its going to be. Im relatively new to rendering just been doing internals for years.
Any advice would be good
 
Best way to learn is by experience! Just have go...
 
Discuss with customer. Communication skills etc. Explain you want to give a fair price but need to earn a living. Maybe remove a section with them present.
Time is money always.

Your welcome
 
used to do per price. but now i say fairest way is.

x amount per man per day plus skip and tool hire. i give them an estimate of how many days and explain had it before where id quote sat 7 days but takes 10 and had other way where would only take 3 days...

that way no one loses out
 
Please don’t render somebody’s house if you don’t know what you’re doing! It’s not skimming and you could leave some poor people in bits! I
 
I just hack off on metre rate just add it on to my render metre rate