Just finished a 5 day plastering course and am practicing by gutting and rebuilding my room from scratch.
Started to level the old brickwork yesterday --using bonding plaster over blue grit, and dots as a guide; but ended up 1/2 a bag shy before I could finish all the leveling. So that killed my skimming that day!
To 'try' and rectify this, I've added 3:1 Unibond Super PVA (18h later, when I got more bonding) which I'm leaving to cure till tomorrow.. then I'll add a second coat of 3:1 to go tacky before continuing bonding/skimming.
Any issues with this approach?
Will the PVA in-between bonding/skimming prevent the first bonding coats from drying properly (or other problems)?
Any feedback would be most useful
Thx
Started to level the old brickwork yesterday --using bonding plaster over blue grit, and dots as a guide; but ended up 1/2 a bag shy before I could finish all the leveling. So that killed my skimming that day!

To 'try' and rectify this, I've added 3:1 Unibond Super PVA (18h later, when I got more bonding) which I'm leaving to cure till tomorrow.. then I'll add a second coat of 3:1 to go tacky before continuing bonding/skimming.
Any issues with this approach?
Will the PVA in-between bonding/skimming prevent the first bonding coats from drying properly (or other problems)?
Any feedback would be most useful

Thx