dmplastering
Member
Got a small scratch render job to do in a couple weeks onto block work. Now I've done a fair bit of it, but when I worked for a firm and they just ordered it by the lorry load. I'm going to use base coat then top coat the next day. Customer wants 8mm base and 10mm scraped back to 8mm top coat. The job is roughly 30m2. After reading up a bit about coverage I'm guessing I may be a little short. I've told them to order 25 bag as I thought it was 1.5-2m2 per bag?
Edited to say 25 bag of each
Edited to say 25 bag of each