Yeah we was on there for a bit but the job was terrible, got 3/4 through 2 blocks after having 2 days worth of materials delivered once a week for months before a complete stop, run by some 1 who was down in england and only contactable once a week if lucky and seen on site every 2-3 weeks for 1 day promising things will change. The other subby and his 4 squads of polish got kicked off site due to filling gas flues with render & terrible work. We were asked to clean up their mess (impossible) we held on due to prospects of the job running smoothly and it never happened so we left and unpaid. Absoulute joke.
Apparently it is running normal again now due to agreed funding by the council but if it is 10% of what it used to be the whole site will go tits up again.