We have expressed our concerns to the contractor, and the architect has been informed that we have requested a disclaimer to our contract in relation to any problems that may occure in the future in veiw of possible inclement/cold weather..
They seem keen to press on still, and are talking about leaving the floor for at least 6 weeks for any further work continues on it.
We are looking at laying 150mm in 3 layers with leanish mix and ramming each one into the other green ( wacker plate) Meshed and finished on top as if screeding.Thinking that this will speed up drying times .
There is no UFH in this make up , and the final floor is flags.