We are on a job priced for 11mm hardwall + skim on blockwork.

It turns out the bricky put the walls up with his eyes shut and we are dubbing out upto 20mm in places. The contractor is shrugging his shoulders...

how much extra should we be charging
and more importantly
how do we convince him how much we have done as most of the walls are now set....?
 
Double it, get a as quantity guy to verify, got stung myself for this in 2010' put tonnes on for nothing, still feel like a mug.
 
You'll get less than you're floating rate, its too late tbh they won't be able to charge because they can't prove it and there's not many extras in jobs nowadays people want a price and that's it
 